[RE-wrenches] Code Question
Brian Mehalic
brian at solarenergy.org
Thu Mar 4 15:22:24 EST 2021
300.18
Brian
> On Mar 4, 2021, at 1:11 PM, Drake <drake.chamberlin at redwoodalliance.org> wrote:
>
> Hello Wrenches,
>
> I believe it is a code requirement to install conduits in their entirety before pulling wire through, and that this applies to all types of rigid conduit.
>
> Is this correct? Does anyone know where in the NEC this is stated?
>
> Thank you,
>
> Drake
>
>
> Drake Chamberlin
> Athens Electric LLC
> OH License 44810
> CO ME Licence 4526
> NABCEP Certified Solar PV
> 740-448-7328
> http://athens-electric.com/
>
> _______________________________________________
> List sponsored by Redwood Alliance
>
> List Address: RE-wrenches at lists.re-wrenches.org
>
> Change listserver email address & settings:
> http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
>
> There are two list archives for searching. When one doesn't work, try the other:
> https://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/
> http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org
>
> List rules & etiquette:
> http://www.re-wrenches.org/etiquette.htm
>
> Check out or update participant bios:
> http://www.members.re-wrenches.org
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches_lists.re-wrenches.org/attachments/20210304/48f90d0f/attachment.htm>
More information about the RE-Wrenches
mailing list