[RE-wrenches] Code Question
Drake
drake.chamberlin at redwoodalliance.org
Thu Mar 4 14:21:33 EST 2021
Hello Wrenches,
I believe it is a code requirement to install conduits in their
entirety before pulling wire through, and that this applies to all
types of rigid conduit.
Is this correct? Does anyone know where in the NEC this is stated?
Thank you,
Drake
Drake Chamberlin
Athens Electric LLC
OH License 44810
CO ME Licence 4526
NABCEP Certified Solar PV
740-448-7328
<http://athens-electric.com/>http://athens-electric.com/