[RE-wrenches] Supply side denial

Kristopher Schmid solman at legacysolar.com
Tue Oct 27 18:27:31 EDT 2020


Hi All,

I have a utility that is hinting that they are going to deny my
interconnection application with a supply side connection and require a
load side.  Has anyone seen this before?

(Proposed interconnection would be with Milbank step lugs in a 200 A socket
and a 60 A fused disconnect within 10 feet.)

If they refuse it, i am thinking that registering a complaint with the
Wisconsin PSC may be appropriate.

Kris


Shine On!

Kris Schmid
Legacy Solar, LLC
137 West 1st Avenue
Luck, WI 54853
www.legacysolar.com
715-653-4295
NABCEP Certified PV Installation Professional
Licensed Wisconsin Master Electrician
BSEE
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches_lists.re-wrenches.org/attachments/20201027/794f5dcd/attachment.htm>


More information about the RE-Wrenches mailing list