[RE-wrenches] Optimal 200 or 225 Amp Square D MSP All-in-One meter for CT Clamps

Gregory Seelhorst gseelhorst at gmail.com
Wed Feb 17 08:23:33 PST 2016


Wrenches -

Does anyone know of a good spec for a 200 or 225A Square D Main Service
Panel which has feeders between the meter and Main Disconnect and would be
ideal for 150A CT clamps for monitoring whole house consumption?

I'm finding most MSPs have a short, flat bus between the meter and Main
Disconnect which requires the Rigowski Coil (requiring more expensive and
unreliable hardware).

Thank you for your help in advance.

Regards,

Greg Seelhorst
NABCEP PV Installation Professional #092907-16
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20160217/0eefef61/attachment-0001.html>


More information about the RE-wrenches mailing list