Wrenches -
Does anyone know of a good spec for a 200 or 225A Square D Main Service
Panel which has feeders between the meter and Main Disconnect and would be
ideal for 150A CT clamps for monitoring whole house consumption?
I'm finding most MSPs have a short, flat bus between the meter and Main
Disconnect which requires the Rigowski Coil (requiring more expensive and
unreliable hardware).
Thank you for your help in advance.
Regards,
Greg Seelhorst