[RE-wrenches] Lumos LSX250 modules

Chris Worcester chris at solarwindworks.com
Sun Jun 15 11:32:58 PDT 2014


Hi Corey,

Good to hear you’re also using Lumos, I know the rail alignment is what is going to make or break the install, maybe a light weight plywood template is in order! I have requested the slotted rails, the unperforated ones just don’t make sense. The tip on removing part of the rubber bumper to run wiring is a good one, thanks!

 

Chris Worcester

Solar Wind Works

NABCEP Certified PV Installer

Office 530-582-4503

Cell 530-448-9692

Fax 530-582-4603

www.solarwindworks.com

chris at solarwindworks.com

 

From: RE-wrenches [mailto:re-wrenches-bounces at lists.re-wrenches.org] On Behalf Of Corey Shalanski
Sent: Friday, June 13, 2014 12:42 PM
To: re-wrenches at lists.re-wrenches.org
Subject: Re: [RE-wrenches] Lumos LSX250 modules

 

Chris,

 

We have done a few Lumos projects down here in the Gulf South, where snow removal is not an issue. Please see attached for an example rooftop installation - these modules definitely end up looking pretty "slick".

  <https://mailfoogae.appspot.com/t?sender=aY3NoYWxhbnNraUBqb3VsZS1lbmVyZ3kuY29t&type=zerocontent&guid=4ddc6bae-1d89-4a30-9e25-04aa9336e0a1> ᐧ

 

I would echo August's comment about the rail alignment. The module mounting holes allow for a bit of wiggle room, enough to square up any off-kilter modules but not enough to make up for misaligned/non-parallel rails. I would also highly recommend the slotted rails (don't know if the non-slotted rails are even still an option).

 

As you pointed out wire management is simplified with their rails. Wires running perpendicular to the rails can be accommodated by removing one or more of the rubber bumpers to create a gap between the module and rail. We have also used suction cups to assist in lifting these modules to the roof - at 60 pounds apiece they are noticeably heavier that most of other modules we deal with.

 

--

Corey Shalanski

Joule Energy

New Orleans, LA

 

On Fri, Jun 13, 2014 at 12:38 PM, <re-wrenches-request at lists.re-wrenches.org> wrote:


Message: 4
Date: Thu, 12 Jun 2014 13:34:44 -0700
From: August Goers <august at luminalt.com>
To: RE-wrenches <re-wrenches at lists.re-wrenches.org>
Subject: Re: [RE-wrenches] Lumos LSX250 modules
Message-ID: <0159cb59674b658f52fe85632f56bc3b at mail.gmail.com>
Content-Type: text/plain; charset="utf-8"

Hi Chris,



We have a complex 86 kW commercial job with Lumos 250s we?ve just kicked
off. We have not installed them yet so I can?t offer a whole lot of advice
except that the module leads won?t reach each other in landscape
orientation so I?d recommend a standard portrait layout. The rails also
need to line up perfectly since the modules mount with the four
through-holes.



We will be landing our panels in about 3 weeks so I should know more then,
feel free to ping me if you haven?t made your decision yet.



Best,



August

Luminalt

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20140615/7afcce9f/attachment-0003.html>


More information about the RE-wrenches mailing list