OK, even though the solar racking manufacturers do not detail nailing the
flashings to the roofs in their installation manuals and on-line videos, Oatey
does publish a document which says "One nail or staple in each bottom corner is
appropriate."
Nick Soleil
Project Manager
Advanced Alternative Energy Solutions, LLC
PO Box 657
Petaluma, CA 94953
Cell: 707-321-2937
Office: 707-789-9537
Fax: 707-769-9037
________________________________
From: North Texas Renewable Energy Inc <ntrei at 1scom.net>
To: RE-wrenches <re-wrenches at lists.re-wrenches.org>
Sent: Wed, July 28, 2010 6:33:23 AM
Subject: Re: [RE-wrenches] Flashings- to nail or not to nail
Nick
We not only use roofing nails at the bottom corners of metal flashing but
sealant around the top and side edges of the face down side. It keeps potential
water seeping from uphill away from the lag penetration[s]. We also seal around
every shingle edge we pull up or trim off around the flashing.
In the words of Mark Graham Assoc. Executive Dir of the National Roofing
Contractors Assoc emphasized in his presentation at the AEE conference in Feb,
anything less "...is installing roof leaks."
Yep, it's more work than slapping down L-feet, about 5 minutes per standoff
start to finish, but metal flashed standoffs are the only way we'll attach PV
on 3-tab asphalt roofs. It's often as time consuming finding the rafters as it
is mounting the footings and flashing.
....my $0.02 [compounded over 20 years]
Jim Duncan
NABCEP Certified Solar PV
Installer No.31310-57
TECL 27398
North Texas Renewable Energy
486 W.N. Woody Road
Azle Texas 76020
Since 1993
ntrei at 1scom.net
817.917.0527
www.ntrei.com
-----Original Message-----
>From: re-wrenches-bounces at lists.re-wrenches.org
>[mailto:re-wrenches-bounces at lists.re-wrenches.org]On Behalf Of Nick Soleil
>Sent: Tuesday, July 27, 2010 9:47 PM
>To: RE-wrenches
>Subject: Re: [RE-wrenches] Flashings- to nail or not to nail
>
>
>HI Wrenches:
> My crew wants to nail all the flashings on our footings, but I am
>resisting. Do you guys have any strong feelings about that.
>
> Nick Soleil
>Project Manager
>Advanced Alternative Energy Solutions, LLC
>PO Box 657
>Petaluma, CA 94953
>Cell: 707-321-2937
>Office: 707-789-9537
>Fax: 707-769-9037
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20100728/75925f09/attachment-0004.html>
More information about the RE-wrenches
mailing list