William Miller
william at millersolar.com
Fri Dec 11 16:31:12 PST 2009
Friends:
I just received a plan correction for a grid-tie permit application wherein
the inspector is questioning compliance with section 225. Below is the
text of the correction notice:
The existing panel C in the pump house must comply with NEC 225.31. 225.32
& 225.33. Show the number of existing circuits and/or the disconnecting
means for panel C.
Has anyone ever had experience with this section being applied to a
grid-tie system? The inverters will be inside a pump house remote from the
main residence.
Thanks in advance.
William Miller
Please note new e-mail address and domain:
William Miller
Miller Solar
Voice :805-438-5600
email: william at millersolar.com
http://millersolar.com
License No. C-10-773985
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20091211/8494cc2b/attachment-0002.html>
More information about the RE-wrenches
mailing list