I just received a plan correction for a grid-tie permit application
wherein the inspector is questioning compliance with section 225. 
Below is the text of the correction notice:<br><br>
<font size=3><i>The existing panel C in the pump house must comply with
NEC 225.31. 225.32 & 225.33. Show the number of existing circuits
and/or the disconnecting means for panel C. <br><br>
</i></font>Has anyone ever had experience with this section being applied
to a grid-tie system?  The inverters will be inside a pump house
remote from the main residence.<br><br>
Thanks in advance.<br><br>
William Miller<br><br>