Hi William,
We have changed equipment on several projects (while keeping total power
just under the original application, as you stated), and have achieved NEM2
PTO from PG&E. These were all projects sold by other contractors (with
various wacky equipment specified) which we took over because the other
contractors could not perform (went out of business, etc).
Regarding the used inverter: if the customer is ok with it, I assume no one
else needs to know that it's used. However, one concern with PG&E is that
the inverter model number needs current grid support / Rule 21 / 1741 SB
listing. That's one thing they will for sure get hung up on, so it may
require you to switch to a new(er) inverter.
Good luck!
Best,
Blake
Blake Gleason, PE | Employee Owner
Director of Innovation and Technical Excellence
O: 510-845-2997 x128
C: 510-867-5878
[image: sunlightandpower.com] <http://sunlightandpower.com/>
<https://linktr.ee/SLP_Socials>
1035 Folger Ave.
Berkeley, CA 94710
www.sunlightandpower.com
License #326203
<https://benefitcorporationsforgood.com/> [image:
https://www.amicussolar.com/] <https://www.amicussolar.com/> [image:
https://calssa.org/] <https://calssa.org/>
On Thu, Apr 9, 2026, 7:13 PM William Miller via RE-wrenches <
re-wrenches at lists.re-wrenches.org> wrote:
> Dear Cali-Wrenches:
>
>
>
> I finally got my Unirac RM10EVO ballasted ground mount approved. Unirac
> offered a wet stamp service for a modest $350 and that carried the day with
> the building department.
>
>
>
> Now I need to submit the paperwork to PG&E. The NEM application was done
> three years ago and the equipment we specified then is of course no longer
> available. PG&E has a rule that you can substitute equipment if the rated
> power is no greater than the application or no less than 80% of the
> application, and we meet that criteria.
>
>
>
> The portal will ask if I am using the original equipment. The last one I
> did I fibbed.
>
>
>
> Have any of you changed equipment for an existing NEM application? Was it
> a big deal or not? We ended up with a used SB600US. Will the used
> equipment be a problem?
>
>
>
> Thanks again for all of the great advice.
>
>
>
> William
>
>
>
> William Miller
>
> Miller Solar
>
> www.millersolar.com
>
> CA License C-10 77398
>
>
> _______________________________________________
> List sponsored by Redwood Alliance
>
> Pay optional member dues here: http://re-wrenches.org
>
> List Address: RE-wrenches at lists.re-wrenches.org
>
> Change listserver email address & settings:
> http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
>
> There are two list archives for searching. When one doesn't work, try the
> other:
> https://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/
> http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org
>
> List rules & etiquette:
> http://www.re-wrenches.org/etiquette.htm
>
> Check out or update participant bios:
> http://www.members.re-wrenches.org
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20260409/766aaf89/attachment.htm>
More information about the RE-wrenches
mailing list