Hello Drake,

Making adjustments like this would be best to have a review by our support team. Reducing the global AC output of the inverter involves a thorough understanding of the installation site and the overall goals for the system. To determine the best course of action, we’ll need to gather some key information, some of these questions would include:

What are you aiming to achieve with this installation?

How is the system currently configured?

Is this requirement expected to change in the future?

Is the inverter operating in grid-tied or off-grid mode?

Depending on the site’s purpose and configuration, different approaches may be more suitable. Some customers benefit more from setting a max A discharge rate, using the load limit power setting (if supported by the inverter firmware), or receiving a command to reduce the global AC output.

Each option has specific requirements, and in some cases, these changes may have a permanent effect on the inverter. That’s why it’s critical for our team to fully understand the setup before recommending a solution.


Best Regards,

Jharen Poole
Applications Engineer II
972-575-8875
[cid:e6d548ff-5ca8-4e76-971f-8cf4366c916c]
________________________________
From: drake.chamberlin at redwoodalliance.org <drake.chamberlin at redwoodalliance.org>
Sent: Wednesday, June 18, 2025 9:29 AM
To: Poole, Jharen <Jharen.Poole at sol-ark.com>
Cc: RE-wrenches <re-wrenches at lists.re-wrenches.org>
Subject: Re: [RE-wrenches] Sol-Ark Technical Question

Caution: This email is from an external source.



Hello Jharen,

Members of the RE Wrench list are still hoping for an answer to the question of how to program a limit on the AC output of Sol-Ark inverters. Can you send an explanation to me, to post on the list, or post it yourself if you are able.

Thank you,

Drake


Drake Chamberlin

Athens Electric LLC

Ohio Electrical Contractor’s License 44810

NABCEP Certified PV Installation Professional

---



On 2025-06-04 18:29, drake.chamberlin at redwoodalliance.org wrote:

Hi Jharen,

Paul Wood will be contacting you. We talked during the system redesign process. Paul is one of the physical installers of the system.

This system has 9 Sol-Ark 15K inverters. Breakers are tripping on the input and output.


Thank you,

Drake


Drake Chamberlin

Athens Electric LLC

Ohio Electrical Contractor’s License 44810

NABCEP Certified PV Installation Professional


---



On 2025-06-04 17:03, Poole, Jharen via RE-wrenches wrote:

Hello,

I'd like to get this question resolved for you as quickly as possible. Could you please reach out to me at jharen.poole at sol-ark.com with the details of how much power or amperage you'd like to limit for this installation? Additionally, please include any relevant information about the inverter and its setup—such as inverter SN, whether it's configured for zero net metering or any other specific setup.

Best Regards,

Jharen Poole
Applications Engineer II
972-575-8875
[cid:17502569716852cd4bb20ae144200974 at redwoodalliance.org]
________________________________
From: RE-wrenches <re-wrenches-bounces at lists.re-wrenches.org> on behalf of Jason Szumlanski via RE-wrenches <re-wrenches at lists.re-wrenches.org>
Sent: Wednesday, June 4, 2025 10:10 AM
To: RE-wrenches <re-wrenches at lists.re-wrenches.org>
Cc: Jason Szumlanski <jason at floridasolardesigngroup.com>; Wodenrobert23 <wodenrobert23 at gmail.com>
Subject: Re: [RE-wrenches] Sol-Ark Technical Question


Caution: This email is from an external source.


If I understand the question correctly, you can use Time of Use to set the maximum charge or sell power in watts for up to 6 time slots. I believe this will limit only the battery charge or discharge rate, however. I don't believe this will limit the total input (loads plus battery charging). You can limit the total sell power with the Grid Sell feature in the System Work Mode settings. The Max Sell Power should limit the total solar export plus battery selling to this setting.

Jason Szumlanski
Principal Solar Designer | Florida Solar Design Group
NABCEP Certified Solar Professional (PVIP)
Florida State Certified Solar Contractor CVC56956
Florida Certified Electrical Contractor EC13013208

On Wed, Jun 4, 2025 at 10:55 AM Drake Chamberlin via RE-wrenches <re-wrenches at lists.re-wrenches.org<mailto:re-wrenches at lists.re-wrenches.org>> wrote:
Sol-Ark has not been available to answer a question.

We need to reduce the AC amperage input and output on a system. Tech support had assured us that this can be done, prior to installing the system. It is unclear how to do this.

Does anyone know how to adjust the AC in and AC out maximum amperage on the 15kW Sol-Ark inverters?

--

Drake Chamberlin

Athens Electric LLC

Ohio Electrical Contractor's License 44810

NABCEP Certified PV Installation Professional


--

_______________________________________________
List sponsored by Redwood Alliance

Pay optional member dues here: http://re-wrenches.org

List Address: RE-wrenches at lists.re-wrenches.org<mailto:RE-wrenches at lists.re-wrenches.org>

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

There are two list archives for searching. When one doesn't work, try the other:
https://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/
http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
http://www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
http://www.members.re-wrenches.org


_______________________________________________
List sponsored by Redwood Alliance

Pay optional member dues here: http://re-wrenches.org

List Address: RE-wrenches at lists.re-wrenches.org<mailto:RE-wrenches at lists.re-wrenches.org>

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

There are two list archives for searching. When one doesn't work, try the other:
https://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/
http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
http://www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
http://www.members.re-wrenches.org

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20250620/717ab0aa/attachment-0001.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Outlook-t2yohww0.png
Type: image/png
Size: 82002 bytes
Desc: Outlook-t2yohww0.png
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20250620/717ab0aa/attachment-0002.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Outlook-r2frzgfg.png
Type: image/png
Size: 82002 bytes
Desc: Outlook-r2frzgfg.png
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20250620/717ab0aa/attachment-0003.png>


More information about the RE-wrenches mailing list