Take a look at 690.31(G) - 2014 NEC.
Sincerely,
Glenn Burt
Sent from my 'smart' phone so please excuse grammar and typos.
-----Original Message-----
From: "frenergy" <frenergy at psln.com>
Sent: 5/15/2015 0:25
To: "RE-wrenches" <re-wrenches at lists.re-wrenches.org>
Subject: [RE-wrenches] DC conduit
Esteemed Wrenches,
One of my customers (who is also an Electrical contractor) asked me why metal conduit is required from the combiner to the inverter. In this case the DC run will go under the house in the crawl space before exiting the foundation and up to the DC disco on the inverter. With inverters that incorporate AFCI on the PV side, I couldn't come up with a good answer.
Bill Battagin
Feather River Solar Electric
4291 Nelson St.
Taylorsville, CA 95983
530.284.7849 / 6544 fax
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20150515/ba089197/attachment-0002.html>
More information about the RE-wrenches
mailing list