[RE-wrenches] Gross PV production meter options

Alex Cozine acdc.cozine at gmail.com
Tue Dec 6 23:23:12 PST 2011


Ditto Larry's link:
1 turns meter when PV power sold.
2 turns meter when Battery Power sold.
3 cancels turns when: pulling power to charge battery and using that
battery power for critical loads. (power used from grid is still accounted
for on the utility meter)

side note: for 120V output
you need 2 meters for 240 volt output (one for each output)

Good luck

On Tue, Dec 6, 2011 at 9:59 PM, <wirewiz at gmail.com> wrote:

> David,
>
> Here is a link to what you might be looking for:
> http://www.outbackpower.com/pdf/tech_notes/120_vac_single_inverter.pdf
>
> Larry Liesner
> Wirewiz
> 31 Lincoln St
> Westport, CT 06880
> 203-644-2404
> wirewiz at gmail.com
> www.wire-wiz.com
> NABCEP Certified PV Installer (# 032611-184)
>
>
>
-- 
Alex Cozine
NABCEP Certified Solar PV Installer™\
Journeyman Electrician

Brothers Electric & Solar
brotherselectricsolar.com
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20111206/596a1970/attachment-0004.html>


More information about the RE-wrenches mailing list