Another issue I have locally is the utility telling me "you can turn it on
to test it, but you can't leave it on until inspected and the meter is
changed out". That is the extent of their policy. Nothing in writing, which
is what I am pushing for. What do other utils nationwide have? Formal
maximum turn-on / test / turn-off time periods before inspection? In
writing? Or seat of the pants?
Kirk Herander
VT Solar, LLC
dba Vermont Solar Engineering
NABCEPTM Certified installer Charter Member
NYSERDA-eligible Installer
VT RE Incentive Program Partner