[RE-wrenches] The perfect solar ready roof
Chad Waits
chadwaits at netzerosolar.net
Wed Oct 20 06:42:58 PDT 2010
How about adding blocking between the TJI's and lagging to that? That has
worked for us in the past.
But I think that might be a mute point if you are adding a metal roof.
Suggest a standing seam roof and attach with S5! clips. That would be the
cleanest and no penetrations!
Chad Waits
Net Zero Solar
520.270.4873
chadwaits at netzerosolar.net
From: re-wrenches-bounces at lists.re-wrenches.org
[mailto:re-wrenches-bounces at lists.re-wrenches.org] On Behalf Of Chris Daum
Sent: Tuesday, October 19, 2010 7:58 PM
To: 'RE-wrenches'
Subject: [RE-wrenches] The perfect solar ready roof
Dear Wrenches:
I have a composite (shingle) roof at hand, and the owner wants to upgrade it
to a metal roof and install a 5kw+ array on it. The rafters are those (sort
of) particle board I-beams covered with 1/2" plywood (and shingles). What's
the best metal roofing you could suggest--and would you beef up the wood to
lag into?
Thanks for all your input.
Chris Daum
Oasis Montana Inc.
406-777-4309
406-777-0830 fax
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20101020/4aa319d3/attachment-0004.html>
More information about the RE-wrenches
mailing list