[RE-wrenches] dual stacked inverters on 208V service
Nik Ponzio
nponzio at buildingenergyus.com
Thu Dec 31 13:15:18 PST 2009
Hi Gang,
I have a problem. We are installing a gridtie PV system with 2
battery-based inverters for 240V. The service coming in to the condo is
120/208 split-phase fed from 3-phase 208 in main building. The master
inverter pickups up L1 but the slave inverter will not sync. What am I
missing?
Thanks and Happy New Year to all!