Huh.....

This seems extremely biased (dah).  I am curious how it is that the DOB
justifies this decision.  Currently, no other completed electrical system is
required to under go such testing as long as ALL COMPONENTS USED IN THE
SYSTEM ARE UL CERTIFIED/APPROVED FOR THAT PURPOSE.  

Would this be a case where the inspectors are not properly educated as to
what to look for?  Therefore, they are CYAing?  I say this because we have
corrected (rewired, including replacing/installing disconnects where there
were none) several Astropower/Home Depot systems in the New York/New Jersey
area.

It would seem reasonable that an explanation be forthcoming.  Once you get
one, perhaps speaking w/John Berdner @ SMA regarding the explanation.  I
suggest this only because he sits on one of the NEC code determination
boards.  One may be able to use the NEC to pleasantly argue against the DOBs
position.

Just a thought.

Barbra K. Kerr
President
Stellar Power & Heating
PO Box 1992
Twain Harte, Ca 95383
1-800-886-2258
209-586-9607 Fax
858-337-5097 Cell
 


- - - -
To send a message: RE-wrenches at topica.com

Archive of previous messages: http://lists.topica.com/lists/RE-wrenches/read

List rules & how to change your email address: www.mrsharkey.com/wrenches/etiquette.php

Check out participant bios: www.mrsharkey.com/wrenches/

Hosted by Home Power magazine

Moderator: michael.welch at homepower.com
--^----------------------------------------------------------------
This email was sent to: michael.welch at homepower.com

EASY UNSUBSCRIBE click here: http://topica.com/u/?bz8Qcs.bz9JC9.bWljaGFl
Or send an email to: RE-wrenches-unsubscribe at topica.com

For Topica's complete suite of email marketing solutions visit:
http://www.topica.com/?p=TEXFOOTER
--^----------------------------------------------------------------






More information about the RE-wrenches mailing list