Jerry C wrote:
> They stubbed 1 1/4" rigid metallic conduit up through
the same concrete that the 8" sched 40 poles were in.
The 1 1/4" conduit had pvc 2 mil tape wrapped around
it. The 8" schedule 40 did not. I have observed this practice, but
don't fully understand it either.
All:
This practice is what I was referring to in a previous post.....
The difference between "Structural" and "Electrical" steel components in
concrete. The Contractor followed common practice (right practice??) in
this application. He wrapped the conduit but not the structural steel.
I'm glad you brought it up, Jerry. It is a perfect example of what this
thread is about!
Cloudy in Sacto....
Matt Lafferty
Universal Energies Institute
mlafferty at universalenergies.com
(916) 422-9772
(916) 628-7694 Cell
(916) 914-2247 Fax
www.universalenergies.com
- - - -
To send a message: RE-wrenches at topica.com
Archive of previous messages: http://www.topica.com/lists/RE-wrenches/
List rules & etiquette: http://www.mrsharkey.com/wrenches/etiquete.htm
Check out participant bios: www.mrsharkey.com/wrenches/index.html
Hosted by Home Power magazine
Moderator: michael.welch at homepower.com
--^----------------------------------------------------------------
This email was sent to: michael.welch at homepower.com
EASY UNSUBSCRIBE click here: http://topica.com/u/?bz8Qcs.bz9JC9.bWljaGFl
Or send an email to: RE-wrenches-unsubscribe at topica.com
TOPICA - Start your own email discussion group. FREE!
http://www.topica.com/partner/tag02/create/index2.html
--^----------------------------------------------------------------
More information about the RE-wrenches
mailing list