cwarfel
cwarfel at entech-engineering.com
Mon Nov 5 11:15:04 EST 2018
Hi Bill, It's smaller than NEC 691covers, so I would think all the same
rules apply (Not an engineered, stamped allowance). Chris
On 11/5/2018 10:07 AM, frenergy wrote:
> Hey folks,
>
> I've been asked to inter-tie a system to a 600 amp 480V
> delta panel. Do all the same rules apply (Backfeed max 20%, keep
> inter-tie breaker farthest from panel grid feeders, anything else??).
> Proposed system size is about 35-40KW. Its actually a bazillionaire's
> residence.
>
> TIA
>
> Bill
>
> Feather River Solar Electric
> Bill Battagin, Owner
> 4291 Nelson St.
> Taylorsville, CA 95983
> 530.284.7849
> CA Lic 874049
> www.frenergy.net
>
>
> ---
> This email has been checked for viruses by Avast antivirus software.
> https://www.avast.com/antivirus
>
>
> _______________________________________________
> List sponsored by Redwood Alliance
>
> List Address: RE-wrenches at lists.re-wrenches.org
>
> Change listserver email address & settings:
> http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
>
> List-Archive:
> http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html
>
> List rules & etiquette:
> www.re-wrenches.org/etiquette.htm
>
> Check out or update participant bios:
> www.members.re-wrenches.org
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches_lists.re-wrenches.org/attachments/20181105/8d394eee/attachment.htm>
More information about the RE-Wrenches
mailing list