[RE-wrenches] Clearance clarification please
Sam Haraldson
sam at onsiteenergyinc.com
Tue Apr 3 18:07:23 EDT 2018
Chris,
What AHJ are you designing this for? We're only required to follow this
IFC section in certain cities. Keep in mind there is a 2018 IFC as well as
older versions. The 2018 is more favorable to us as designers and
installers as it's not simply a 36" setback but in some cases can be as
little as 18" at the ridgeline.
- Sam
On Tue, Apr 3, 2018, 13:52 <chris at oasismontana.com> wrote
> What section of the Code relates to the 3' clearance for a solar array? …as
> in, the roof area around the array. I’ve been scrutinizing the NEC til
> my eyes are crossed…..
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches_lists.re-wrenches.org/attachments/20180403/e70aeee2/attachment.htm>
More information about the RE-Wrenches
mailing list