Jeremy,
Not sure if this would work..... but.... How about feeding the hydro output
into a large industrial battery charger or chargers. They are available in three
phase.
Modify the charger by eliminating the stepdown transformer. Basically what you
need is a rectifier. Then feed the resulting DC to a conventional solar grid-tie
inverter.
As Jay implied, it can be quite complicated and expensive to sync a hydro with
the grid. The utility's typically require sophisticated protective relays which
require annual testing by utility approved venders. The hydro I help service
pays $1500.00 each time this has to be done. If you can find a way to do it
using UL approved inverters, you may save everyone many tears. SMA Windy Boy and
Power One wind inverter systems work in a similar way.
Dick Ratico
Solarwind Electric
--- You wrote:
Wrenches,
Got a phone call from a gentleman that is in need of a device that will take
240v 60hz and synch with the local utility.
I guess kind of like a grid tie inverter, but AC in not DC input.
Any ideas?
Jeremy
All Solar Inc.
CO, USA
_______________________________________________
List sponsored by Home Power magazine
List Address: RE-wrenches at lists.re-wrenches.org
Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org
List rules & etiquette:
www.re-wrenches.org/etiquette.htm
Check out participant bios:
www.members.re-wrenches.org
--- end of quote ---
More information about the RE-Wrenches
mailing list