Hi boB,<br><br>
I will keep putting an SPD on each string and on the AC line. Sometimes
my systems end up with a lot of blue lights hanging from a wiring
gutter!<br><br>
Have you ever heard of any problems using the Midnite SPDs with Sunny Boy
TL series inverters? So far, I don't think I've had a problem, although
one TL-22, on a large metal roof, had arc fault protector trips.
<br><br>
Thanks,<br><br>
Drake<br><br>
<a name="_MailAutoSig"></a>Drake Chamberlin<br>
<i>Athens Electric LLC<br>
OH License 44810<br>
CO License 3773<br>
NABCEP Certified Solar PV <br>
740-448-7328<br>
</i><a href="http://athens-electric.com/">http://athens-electric.com/</a>
<br>
&nbsp;<br><br>
<br>
At 01:39 PM 10/9/2018, you wrote:<br>
<blockquote type=cite class=cite cite="">Content-Type:
multipart/alternative;<br>
&nbsp;boundary=&quot;------------98C0DCEF93B9ECF248E0580B&quot;<br>
Content-Language: en-US<br><br>
<br>
For an inverter with two MPPT inputs, you will need to treat the
negatives and positive lines separate unless<br>
the manufacturer says something else.&nbsp; That means one&nbsp; SPD per
array unfortunately.&nbsp; Negative and positive connect<br>
to separate leads of the SPD and then ground in the middle.&nbsp; As both
positive and negative PV lines rise together<br>
relative to ground, the SPD is supposed to clamp that rise to below the
equipment's hi-pot voltage that they test<br>
to at the factory.&nbsp; (i.e. common mode voltage rise) All wires except
for ground (chassis) of the equipment are tied <br>
together and the hi-pot machine (sort of like a Megger ?) applies the
high voltage between all those wires on one <br>
side and ground on the other to make sure the insulation doesn't break
down inside the equipment.&nbsp; <br>
This hi-pot test goes for AC&nbsp; utility input/output connections and
DC from the PV input side.&nbsp; <br><br>
The SPD&nbsp; has to clamp plus and minus and AC inputs to a lower
voltage than this hipot rating but higher voltage<br>
than lines will see differentially in voltage.&nbsp; Remember that in a
3-wire SPD, there is two sets of MOVs in series and<br>
the center is tied to ground.&nbsp; If one MOV starts conducting at say,
500 volts DC then you can apply up to 1000<br>
volts&nbsp; between the hot leads.&nbsp; Each plus and negative line can
rise up to 500 volts from the lightning before they<br>
start to clamp.&nbsp; The&nbsp; bigger the lightning strikes effect, the
more current will be applied to the MOVs though and<br>
the clamp voltage will rise somewhat.&nbsp; That's why the SPD arrestor
voltage should be well below the hi-pot voltage,<br>
whatever that is...&nbsp; Hi-pot voltages are quite a bit higher than the
operating voltage.&nbsp; For example, All Classic CC's<br>
are tested to 2270 volts DC from hot lines to ground.&nbsp; It's
something like double the operating voltage plus 1000V<br>
and multiply by 1.414 for DC rating.....&nbsp; I'm going off memory so
don't quote me on that but something like that.<br><br>
I think that Ray has the right idea about short connections like from the
local generator.&nbsp; Battery also.<br>
Just apply SPDs to anything that goes outside like an antenna.<br><br>
boB<br><br>
<br>
On 10/9/2018 8:26 AM, cwarfel wrote:<br>
<blockquote type=cite class=cite cite=""><br>
<font face="Verdana">I think something on the order of 90+% lightning
strikes come from the utility feed, not the dc side. That has to be
ignored if in a high strike area or grid isolated. </font><br><br>
On 10/8/2018 10:37 PM, Ray wrote:<br>
<blockquote type=cite class=cite cite=""><br>
I believe you can use the SPD 300 AC on 2 strings, if PV neg is
grounded.&nbsp; You would connect the green to ground (or PV neg) and
then connect the red to one string pos, and connect the black to the
other string pos.&nbsp; This would be limited to 300 v also.&nbsp; I
haven't tried that exact configuration, but I have used the 300 AC to
protect both the AC in and AC out on 120 vac inverters.&nbsp; I also
believe you can use a 600 DC version, and wire as I mentioned, but the
LEDs won't light. If you are using ungrounded inverters, then I think you
would need an SPD for each string in order to protect both the pos and
neg of each string, like you've been doing.<br><br>
Maybe someone from Midnite can clarify this.<br><br>
As far as it being worth it, I haven't had lightning related damage since
I started using the Midnite SPDs, and I used to have system damage every
year.&nbsp; If you are not in lightning country, or the install is in a
low spot with less likelihood of taking a hit, you might be able to
skimp.&nbsp; But for some of these off grid ridge top installs, I
consider it a must. Some times I don't install one on the gen circuit, if
its really close.<br><br>
&nbsp; <br><br>
<pre>Ray Walters
Remote Solar
303 505-8760</pre><font face="Courier New, Courier"></font>On 10/8/18
4:03 PM, Drake wrote:<br>
<blockquote type=cite class=cite cite="">Hello Wrenches,<br><br>
Do you use surge arrestors with multi MPPT input string inverters? Do you
put a separate arrestor on each MPPT input? I find it sort of pricey
using a Midnite Solar arrestor on each string, but have been doing that.
Is there a less expensive approach that is effective? <br><br>
I believe the Midnite units are the best. Are they worth the
expense?<br><br>
Thank you,<br><br>
Drake<br>
&nbsp;<br>
&nbsp;<br>
<a name="_MailAutoSig"></a>Drake Chamberlin<br>
<i>Athens Electric LLC<br>
OH License 44810<br>
CO License 3773<br>
NABCEP Certified Solar PV <br>
740-448-7328<br>
</i><a href="http://athens-electric.com/">http://athens-electric.com/</a>
<br><br>
<br><br>
<br>
<pre>_______________________________________________
List sponsored by Redwood Alliance

List Address:
<a href="mailto:RE-wrenches@lists.re-wrenches.org">
RE-wrenches@lists.re-wrenches.org</a>

Change listserver email address &amp; settings:
<a href="http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org">
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org</a>

List-Archive:
<a href="http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html">
http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html</a>

List rules &amp; etiquette:
<a href="http://www.re-wrenches.org/etiquette.htm">
www.re-wrenches.org/etiquette.htm</a>

Check out or update participant bios:
<a href="http://www.members.re-wrenches.org">
www.members.re-wrenches.org</a>

</pre><font face="Courier New, Courier"></font></blockquote><br><br>
<br><br>
<pre>_______________________________________________
List sponsored by Redwood Alliance

List Address:
<a href="mailto:RE-wrenches@lists.re-wrenches.org">
RE-wrenches@lists.re-wrenches.org</a>

Change listserver email address &amp; settings:
<a href="http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org">
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org</a>

List-Archive:
<a href="http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html">
http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html</a>

List rules &amp; etiquette:
<a href="http://www.re-wrenches.org/etiquette.htm">
www.re-wrenches.org/etiquette.htm</a>

Check out or update participant bios:
<a href="http://www.members.re-wrenches.org">
www.members.re-wrenches.org</a>

</pre><font face="Courier New, Courier"></font></blockquote><br>
-- <br><br>
<font size=2>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; Christopher
Warfel, PE<br>
&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; ENTECH Engineering, Inc.<br>
PO Box 871, Block Island, RI 02807<br>
&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;
(401)466-8978</font><br>
&nbsp;<br>
<a href="http://entech-engineering.com">
<img src="cid:7.1.0.9.0.20181009165733.062f0440@redwoodalliance.org.1" width=201 height=89 alt="EEI logo">
</a>&nbsp;<br><br>
<br><br>
<pre>_______________________________________________
List sponsored by Redwood Alliance

List Address:
<a href="mailto:RE-wrenches@lists.re-wrenches.org">
RE-wrenches@lists.re-wrenches.org</a>

Change listserver email address &amp; settings:
<a href="http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org">
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org</a>

List-Archive:
<a href="http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html">
http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html</a>

List rules &amp; etiquette:
<a href="http://www.re-wrenches.org/etiquette.htm">
www.re-wrenches.org/etiquette.htm</a>

Check out or update participant bios:
<a href="http://www.members.re-wrenches.org">
www.members.re-wrenches.org</a>

</pre><font face="Courier New, Courier"></font></blockquote><br><br>
<br>
_______________________________________________<br>
List sponsored by Redwood Alliance<br><br>
List Address: RE-wrenches@lists.re-wrenches.org<br><br>
Change listserver email address &amp; settings:<br>
<a href="http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org" eudora="autourl">
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org</a>
<br><br>
List-Archive:
<a href="http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html" eudora="autourl">
http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html</a>
<br><br>
List rules &amp; etiquette:<br>
<a href="http://www.re-wrenches.org/etiquette.htm" eudora="autourl">
www.re-wrenches.org/etiquette.htm</a><br><br>
Check out or update participant bios:<br>
<a href="http://www.members.re-wrenches.org/" eudora="autourl">
www.members.re-wrenches.org</a></blockquote></body>
</html>