Peter,<div>I did a 15kW BIPV install on a home with GE Geko modules in two stages, first (7.7kW) in 2006, and second (7.33kW) in 2008. &nbsp;The 2006 modules were 55 W and the 2008 mods were 66 W.&nbsp;</div><div>I wasn't too impressed with the quality of the GE modules and would prefer not to use them again, which is fine because as you suspected, they no longer make them.</div><div>I was (currently in limbo) working with a client on a 9kW system which i was going to use the Sunteck modules you mentioned, called SolarBlend. &nbsp;Yes, they have a polycarbonate frame (no bonding). &nbsp;Different?, yes. Clever idea?, maybe. &nbsp;What is your hesitation regarding these frames?</div><div><br></div><div>Attention must be paid to the spacing of the horizontal battens that the modules rest on otherwise some cells may be partially covered. &nbsp;Be sure that the roofer knows this and is diligent in spacing them properly. &nbsp;Doesn't hurt to randomly check the spacing for yourself every few rows.</div><div><br></div><div>On a system follow up check, i noticed that some of the 2008 system modules were suffering from sagging frames!!! &nbsp;The lower edge of some frames had sagged down somewhat, allowing various debris to get stuck btwn the frame and the glass. &nbsp;Much of the debris was little bits and pieces of roofing tile and coniferous needles. Thanks for the reminder, I ended up getting tired of unanswered emails/phone calls trying to track someone down to answer for this issue. &nbsp;Does anyone have contact info for a possible warranty claim from GE?</div><div><br></div><div>Also, when it came time to double check string voltages and fire up the system, wouldn't ya know it.... there was a ground fault! &nbsp;And of course all the wiring is now completely concealed within the roof. &nbsp;With some help from SMA support, we were able to determine an approximate location of the fault. Luckily it was close to the end of the last installed string. &nbsp; &nbsp;Soooooo, i started removing tiles and modules to find the fault. &nbsp;After pulling up only 7 or 8 modules (out of a possible 37) i found the problem. &nbsp;A roofing nail for a concrete tile right thru the center of a conductor, and luckily it also went thru the bare bond wire strands as well. &nbsp;Had it not contacted the bond wire.........the fault would not have been found!&nbsp;</div><div><br></div><div>question; &nbsp;this is obviously a hazard, but can someone explain HOW is a 'hot' nail only touching a piece of wood a fire hazard. &nbsp;Is it because of the heat produced from the loose 'connection' creates a fire hazard? &nbsp;Is it possible that the nail could get hot enuf to ignite the wood?&nbsp;&nbsp;is there potential for arcing? ...to what? &nbsp;</div><div><br></div><div>No experience with the Sharp product.</div><div><br></div><div>cheers,</div><div>benn<br><br><span class="ecxecxecxecxEC_Apple-style-span" style="color:rgb(0, 32, 96)">DayStar Renewable Energy Inc.&nbsp;</span><div><div>benn@daystarsolar.ca</div><div>780-906-7807&nbsp;</div><div>HAVE A SUNNY DAY


</div><div><br></div></div><br><br>&gt; From: peter.parrish@calsolareng.com<br>&gt; To: re-wrenches@lists.re-wrenches.org<br>&gt; Date: Wed, 1 Sep 2010 10:05:31 -0700<br>&gt; Subject: [RE-wrenches] PV Modules Compatible with Concrete tile roofs<br>&gt; <br>&gt; About a year and a half ago we did a few installations on flat concrete tile<br>&gt; roofs. We used both the GE product and the Sharp product. We liked the Sharp<br>&gt; product a little better.<br>&gt; <br>&gt; We are now being asked to begin working with a client who is about 6 months<br>&gt; away from new construction and is looking at roof options and PV. He is not<br>&gt; set on the roof type but flat concrete tile is among his options.<br>&gt; <br>&gt; Does anyone have direct experience with PV products that integrate with flat<br>&gt; concrete tile? I don't even know if Sharp and GE still manufacture their<br>&gt; products, and I heard something about Suntech coming out with a plastic<br>&gt; framed product but I would be very wary of that approach.<br>&gt; <br>&gt; - Peter<br>&gt; <br>&gt; Peter T. Parrish, Ph.D., President<br>&gt; California Solar Engineering, Inc.<br>&gt; 820 Cynthia Ave., Los Angeles, CA 90065<br>&gt; CA Lic. 854779, NABCEP Cert. 031806-26<br>&gt; peter.parrish@calsolareng.com  <br>&gt; Ph 323-258-8883, Mobile 323-839-6108, Fax 323-258-8885<br><br></div>                                           </body>
</html>