<font size=3>Nick:<br><br>
Rhetorical questions to follow:<br><br>
If you do not provide string calculations, how do you verify that Voc
will not exceed NEC limits?&nbsp; How do you verify DC feeder
ampacities?&nbsp; Does your jurisdiction not verify such
parameters?&nbsp;&nbsp; We know you have a handle on these factors, but
how about the Johnny-come-latelies trying to take your business?&nbsp;
Should they not be kept to uniform standards meant to protect the safety
of the consumer (and ensure fair competition)?<br><br>
Can you really expect a field inspector or the customer to verify these
parameters?&nbsp; I believe all of these issues are best handled by
stringent plan check.<br><br>
What is more important to you:&nbsp; saving a few bucks in permit fees or
preventing house fires?<br><br>
William Miller<br><br>
<br><br>
<br>
At 05:01 PM 6/15/2010, you wrote:<br>
<blockquote type=cite class=cite cite>Hi Jeff:<br>
&nbsp;&nbsp;&nbsp; My standard permit docs are comprehensive, but do not
include documentation regarding string sizing, thank goodness.&nbsp; A
permit technician/ plan reviewer should not be overseeing string
sizing.&nbsp; You should be thankful that the permit fees are so low,
because that is the best thing a jurisdiction could do to support
PV!&nbsp; <br>
&nbsp;&nbsp;&nbsp; Any fly-by-night, incompetent installer can check
string sizing on the inverter manu's web site.&nbsp; I would suspect
that, regardless of the plan review process, the less experienced
installers will still be accountable to the inspector and their
customer.<br>
&nbsp;<br>
Nick Soleil</font></blockquote></body>