<DIV style="font-family:Arial, sans-serif; font-size:10pt;"><DIV><BR>This is another example of the manufacturers doing whatever and let the installers just deal with it.&nbsp;&nbsp; We just finished a campus wide lighting of all remote signage with custom solar lighting systems.&nbsp; We made up pre-packaged mini-pole mounts with the modules attached so when we got out on site there was only final wiring hookup required.&nbsp; However, several of our systems required different module sizes due to differences in wattage and number of lights.&nbsp; The campus was a 2 hour drive each way from shop, and when we started to assemble everything we found half of the modules had solar wire pigtails and half had USE-2 pigtails.&nbsp;&nbsp;</DIV>
<DIV>&nbsp;</DIV>
<DIV>The pre-assembled M/F wiring extensions we ordered to save having to make our own were also a mix of wire types, and at least half of these wires would not fit through the 2-hole cable connectors we normally install on the combiner boxes as they all had a different outside diameter.&nbsp; Some of the other cables fit very loosely in the 2-hole connectors which will not be a very good moisture barrier.&nbsp;&nbsp;We tried cable glide goop on the largest cables and they still would not fit through these connectors.</DIV>
<DIV>&nbsp;</DIV>
<DIV>This little mix-up lost us another day in field work and a very long return trip that should not have been require.</DIV>
<DIV>&nbsp;</DIV>
<DIV>As we&nbsp;start receiving&nbsp;all this non-standardized stuff, better check everything twice.</DIV>
<DIV>&nbsp;</DIV>
<DIV>Jeff Yago</DIV>
<DIV>DTI Solar</DIV><BR>&nbsp;<BR><HR>Netscape.&nbsp; Just the Net You Need.</DIV>