    ROBIN:<br>
    <br>
    Thanks for the candid response.<br>
    <br>
    I assure you that I <span style="font-size: 11pt; font-family:
      "Calibri","sans-serif";">am one of those "old
      off-grid guys</span>".  <br>
    <br>
    The system I am working on is 120V (L, N) only, and requires the
    inverter/charger to have separate "grid-in/out", "genset in", and
    "inverter output" to the protected loads panel (PLP).<br>
    <br>
    Based on the drawing on the MidNite web site, the SMARB is designed
    for 240V (L1, L2, N). If that's the case, I would use only the "L1"
    path, or perhaps parallel the "L1" and "L2" paths.<br>
    <br>
    I prefer to use the Sunny Island because of its superior battery
    charge management.<br>
    <br>
    Would it be possible to purchase just the <span style="font-size:
      11pt; font-family: "Calibri","sans-serif";">SMARB</span>
    product as an individual part item, or would we need to purchase a
    SMA E-Panel (i.e., MNE250SMA‐OG) with the SMARB pre-installed?<br>
    <br>
    If so, can you provide the ordering part #s and pricing info?<br>
    <br>
    Regards,<br>
    <br>
    <br>
    Gary Willett, PE<br>
    Icarus-Engineering LLC<br>
    Icarus Solar Services LLC<br>
    1124 Gloucester Ct S<br>
    Irving TX  75062-7505<br>
    <br>
    TX PE License # 105617<br>
    NABCEP Certified Solar PV Installer # 031310-246<br>
    <br>
    972-252-2543 (office)<br>
    972-252-4352 (fax)<br>
    214-629-4279 (cell)<br>
    <br>
    <a class="moz-txt-link-abbreviated"
      href="mailto:Gary@Icarus-Engineering.com">Gary@Icarus-Engineering.com</a><br>
    <a class="moz-txt-link-abbreviated"
      href="mailto:Gary@IcarusSolarServices.com">Gary@IcarusSolarServices.com</a><br>
    <br>
    <div class="moz-cite-prefix">On 6/10/15 3:53 PM,
      <a class="moz-txt-link-abbreviated" href="mailto:boB@midnitesolar.com">boB@midnitesolar.com</a> wrote:<br>
    </div>
    <blockquote cite="mid:5578A3C2.2020501@midnitesolar.com" type="cite">
      <meta content="text/html; charset=UTF-8" http-equiv="Content-Type">
      <div class="moz-cite-prefix"><br>
        <p class="MsoNormal"><span
style="font-size:11.0pt;font-family:"Calibri","sans-serif";color:#1F497D">After


            spending a lot of time and money to make the SMA Sunny
            Island work with a grid tie inverter system of twice the
            Sunny Island capacity we dropped the project. The problem we
            had is that the system is complicated and we were spending
            far too much time working with the people in the field as
            well as with our own internal wiring shop. We have made
            changes in our own shop and can now better build these
            systems. We have one customer that uses a lot of these
            because he insists on putting 20 to 24KW of PV on double
            stacked AC coupled Sunny Island systems. We have had no
            issues at all in the field when the SMARB system is properly
            installed. We are very leery of opening this back up to
            installers because it is quit often being installed by
            people who are not really qualified to do this in the field.
            We have begun building these once again for this one
            customer on pre-wired systems. We doubled the price though
            since we were losing money at the old price. We do not know
            if we will open it up for sales as a kit to be installed in
            the field? For a competent installer (old off-grid guys), it
            is a snap. We welcome your comments as we pride ourselves on
            coming up with solutions for problems. This one turned out
            to be tough even for us, but once we had it all figured out,
            it became a nice product, but had a bad history of support
            due to a moving target of how to make it work. <o:p></o:p></span></p>
        <p class="MsoNormal"><span
style="font-size:11.0pt;font-family:"Calibri","sans-serif";color:#1F497D">Robin

            Gudgel<o:p></o:p></span></p>
        <span
style="font-size:11.0pt;font-family:"Calibri","sans-serif";color:#1F497D">MidNite

          Solar</span><br>
        <br>
        <br>
        <br>
        On 6/9/2015 8:33 PM, Gary Willett wrote:<br>
      </div>
      <blockquote cite="mid:5577AFFF.9010808@IcarusSolarServices.com"
        type="cite">Fellow Esteemed Wrenches: <br>
        <br>
        Working on a on-grid battery back-up system with generator where
        client wants to use SMA Sunny Island / Sunny Boy. <br>
        <br>
        Anybody know where to find the MidNite Solar SMA Relay Board
        (MNSMARB), or a functional equivalent? It is intended to be
        installed inside the MidNite SMA E-Panel. <br>
        <br>
        I searched the MidNite site and found the attached document, but
        no other info. <br>
        <br>
        Thanks! <br>
        <br>
        Gary Willett PE <br>
        Icarus Engineering / Solar Services <br>
      </blockquote>
      <br>
      <br>
      <fieldset class="mimeAttachmentHeader"></fieldset>
      <br>
      <pre wrap="">_______________________________________________
List sponsored by Redwood Alliance

List Address: <a class="moz-txt-link-abbreviated" href="mailto:RE-wrenches@lists.re-wrenches.org">RE-wrenches@lists.re-wrenches.org</a>

Change listserver email address & settings:
<a class="moz-txt-link-freetext" href="http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org">http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org</a>

List-Archive: <a class="moz-txt-link-freetext" href="http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html">http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html</a>

List rules & etiquette:
<a class="moz-txt-link-abbreviated" href="http://www.re-wrenches.org/etiquette.htm">www.re-wrenches.org/etiquette.htm</a>

Check out or update participant bios:
<a class="moz-txt-link-abbreviated" href="http://www.members.re-wrenches.org">www.members.re-wrenches.org</a>

</pre>
    </blockquote>
    <br>
  </body>
</html>