<div dir="ltr">Chris....i like your design with the vaults!  Future proof! Do you make your transition to rigid metal conduit in the concrete?  Seems solid!<div>Thanks for sharing...</div><div class="gmail_extra"><br clear="all">
<div><div dir="ltr">Sunny Regards,<br>Kirpal Khalsa<br>NABCEP Certified PV Installation Professional<br>Renewable Energy Systems<br><a href="http://www.oregonsolarworks.com" target="_blank">www.oregonsolarworks.com</a><br>
541-218-0201 m<br>541-592-3958 o</div></div>
<br><br><div class="gmail_quote">On Tue, Oct 8, 2013 at 10:24 AM, Chris Worcester <span dir="ltr"><<a href="mailto:chris@solarwindworks.com" target="_blank">chris@solarwindworks.com</a>></span> wrote:<br><blockquote class="gmail_quote" style="margin:0 0 0 .8ex;border-left:1px #ccc solid;padding-left:1ex">
Hi Ron,<br>
We do a lot of pole mounts, last one was 12' to the bottom of modules, deep<br>
snow country. Typically in a system where there are or has the potential to<br>
expand into more than the original pole mounted array we run a couple of<br>
main PVC conduits underground to a concrete vault, like a C-9, C-24, or<br>
maybe even a C-30 vault. From this vault we distribute the conduits to each<br>
pole mount, or in a larger field like the 8 poles you're mentioning we might<br>
go into a second vault closer to the other end of the field, then branch out<br>
to each pole from it too. We use PVC underground, Rigid metal through the<br>
concrete and up the pole. Hope this helps.<br>
<br>
Chris Worcester<br>
Solar Wind Works<br>
NABCEP Certified PV Installer<br>
Office <a href="tel:530-582-4503" value="+15305824503">530-582-4503</a><br>
Cell <a href="tel:530-448-9692" value="+15304489692">530-448-9692</a><br>
Fax <a href="tel:530-582-4603" value="+15305824603">530-582-4603</a><br>
<a href="http://www.solarwindworks.com" target="_blank">www.solarwindworks.com</a><br>
<a href="mailto:chris@solarwindworks.com">chris@solarwindworks.com</a><br>
<br><br>
</blockquote></div><br></div></div>