<div dir="ltr">Hello,<div><br></div><div>I am in the process of installing a Enphase system that requires center feeding the individual 15 modules circuits. I am wondering about wiring the J-Box.  I need to cut all of the boxes into the center of the runs of Engauge cable and maintain the 6" of free conductor.  To do this, I will need to pull the trunk cable towards the J-Box.  There are a few spots where doing this may pull the inverter connection points to far from the inverter.  It looks like like the spots where this will be a problem is where the circuit of modules is made up of modules from different North-South rows of racking. I took some rough measurements at the end of the day, but haven't really laid the cable out to check if it will really be problem.</div>
<div><br></div><div>I'm sure this is common, and easily fixed, but a conformation from another installer would surely be welcome.</div><div><br></div><div>Thanks,</div><div><br></div><div>Jesse</div></div>