<font size=3>Friends:<br><br>
I have had plan checkers insist I use wet rated wire on rooftops even
though the wire was in either liquid tight or EMT with raintight
connectors.  I did not need to dispute this because we had specified
THHN wire that is also rated THWN for wet locations.  This
discussion makes me think I should have contradicted the requirement
because I am not sure wet rated wire is required inside dry
conduit.  I will be looking this up.<br><br>
I feel that you should not let an AHJ impose a requirement that is not in
the code because then you become bound to the new stricture.  I
realize that an AHJ can impose stricter requirements, but I insist that
it be in writing, required in advance of the job in question and that it
be required universally.  Otherwise, it's anarchy.<br><br>
William Miller<br><br>
<br>
Miller Solar<br>
Voice :805-438-5600<br>
email: william@millersolar.com<br>
<a href="http://millersolar.com/" eudora="autourl">http://millersolar.com<br>
</a>License No. C-10-773985<br>
</font></body>
</html>