<DIV>Brian:</DIV>
<DIV> </DIV>
<DIV>It seems to me that this requires the PE to actually commission the 
system.  A simple wet-stamp on plan submittals is not even indicated by the 
paragraph below, but I am certain is required.  </DIV>
<DIV>Bill, have you had to have a PE provide a commissioning report at the time 
of final inspection for your installations? This is a requirement that 
could arguably make sense for commercial systems, but is a good example of how 
local authorities have carte blanche to overlay egregiously onerous 
requirements if their civic spirit is anti-solar.  </DIV>
<DIV> </DIV>
<DIV>We stopped working in Yorba Linda many years ago.  Aside from 
the city's total and casual disregard for the solar rights act,  
B&S attitude was one of obstruction. FYI, this city is Nixon's 
hometown.</DIV>
<DIV> </DIV>
<DIV>Patrick Redgate</DIV>
<DIV>Ameco Solar</DIV>
<DIV> </DIV>
<DIV>
<DIV>In a message dated 12/19/2009 7:43:48 A.M. Pacific Standard Time, 
wkorthof@eesolar.com writes:</DIV>
<BLOCKQUOTE 
style="BORDER-LEFT: blue 2px solid; PADDING-LEFT: 5px; MARGIN-LEFT: 5px"><FONT 
  style="BACKGROUND-COLOR: transparent" color=#000000 size=2 face=Arial>Yes, 
  Yorba Linda technically requires an electrical PE stamp on PV  
  <BR>projects.<BR><BR>  We've probably done a dozen installations in the 
  city, though I  <BR>don't think they've<BR>enforced the electrical PE 
  requirement on all projects. They do  <BR>require structural<BR>PE on all 
  projects as well, and that requirement is always enforced.  <BR>Big 
  pain.<BR><BR>Yes it's onerous. Yes we hate it. But we keep going.<BR><BR>We 
  have structural and electrical PE engineers available to review and  
  <BR>certify our<BR>plans as needed, so these are just more extra costs helping 
  to drive  <BR>up the cost<BR>of solar.<BR><BR>/wk<BR><BR><BR>>  
  ----- Original Message -----<BR>>  From: William Miller<BR>>  
  To: RE-wrenches<BR>>  Sent: Friday, December 18, 2009 5:05 
  PM<BR>>  Subject: Re: [RE-wrenches] Solar System 
  Certification<BR>><BR>><BR>>  Brian:<BR>><BR>>  I 
  looked up the Municipal Codes 
  (http://www.ci.yorba-linda.ca.us/~ci26/how-do-i/get/get-city-codes <BR>> ) 
  and this requirement is right in there.  I hope you have a  <BR>> 
  provision in your contract that allows for additional billing for  
  <BR>> unanticipated engineering fees.  Everyone should.  If you 
  need  <BR>> language, contact me off line.<BR>><BR>>  
  Fortunately I have never experienced anything like this.  This  
  <BR>> requirement sounds unreasonable.  It is sort of like asking an 
  air  <BR>> conditioning contractor to have the air conditioning unit 
  tested in  <BR>> the field.  Individual solar components are 
  listed.  The combining  <BR>> of the components is facilitated by 
  the manufacturers specifications  <BR>> and on-line sizing tools. 
  Having said that, an amateur can easily  <BR>> screw the design and 
  installation of even the most simple grid-tie  <BR>> system.  
  This provision is the ultimate consumer protection.  It  <BR>> 
  sounds onerous at first but does have a benefit.<BR>><BR>>  Good 
  luck, and give us a hint how much this certification 
  costs.<BR>><BR>>  William 
  Miller<BR>><BR>><BR>><BR>><BR>>  At 01:31 PM 12/18/2009, 
  you wrote:<BR>><BR>>    I am curious if any of you have had to 
  deal with this issue before.<BR>><BR>>    The following is an 
  item we got back from the City of Yorba Linda  <BR>> for a Plan Check 
  correction:<BR>><BR>><BR>>     All electrical solar 
  systems shall be tested and approved by a  <BR>> California Registered 
  Electrical Engineer.  The engineer shall  <BR>> furnish a report 
  stating their name, registration number, its date  <BR>> of 
  expiration, address where the testing occurred and the dates of  <BR>> 
  testing and approval.  Such report shall be presented to the City  
  <BR>> inspector for approval at the time of final inspection.  
  (YLMC  <BR>> 15.28.020)  Note on the plans.<BR>><BR>>  
    All experiences and suggestion are 
  appreciated.<BR>><BR>><BR>><BR>>    Best 
  Regards,<BR>>    Brian C. White<BR>>    Design 
  Engineer - PV Systems<BR>><BR>>    Eagle Roofing 
  Products<BR>>    120 North Auburn Street - Suite 
  212<BR>>    Grass Valley, CA  95945<BR>>    
  Phone: 530-273-2948<BR>>    Cell: 530-575-5550<BR>>  
    e-mail: brianw@eagleroofing.com 
  <mailto:brianw@eagleroofing.com><BR>><BR>>    
  _______________________________________________<BR>> ><BR>><BR>>   ><BR>><BR>><BR>> 
  </FONT></BLOCKQUOTE></DIV></FONT></BODY></HTML>