Mark --<br>It doesn't sound like your crawl-space run is 'readily accessible' either. Could you put a DC disconnect on the exterior before you go inside?<br><br>Rebecca Lundberg<br>Powefully Green, Minnesota<br>
---------------------------------------<br><div class="gmail_quote"><blockquote class="gmail_quote" style="border-left: 1px solid rgb(204, 204, 204); margin: 0pt 0pt 0pt 0.8ex; padding-left: 1ex;">
<br>
Message: 1<br>
Date: Fri, 18 Dec 2009 16:24:30 -0700<br>
From: "Mark Dickson" <Mark@OasisMontana.com><br>
To: "'RE-wrenches'" <<a href="mailto:re-wrenches@lists.re-wrenches.org">re-wrenches@lists.re-wrenches.org</a>><br>
Subject: [RE-wrenches] 690.31E (through a building)<br>
Message-ID: <1811BE33CF8D4796B75549AC52C25F91@OasisMontanaM><br>
Content-Type: text/plain; charset="us-ascii"<br>
<br>
Hello there,<br>
<br>
Due to a lot of concrete and asphalt, we are forced to run our PV source<br>
circuits in through one exterior wall, through a crawl space and out through<br>
the opposite exterior wall to our inverter and disconnect.  We will be using<br>
EMT and will not be making any stops while inside the building.  We will<br>
however need to place a couple of pull-boxes due the various required bends<br>
in excess of 360*.  Will we be required to place a DC disconnect at the<br>
"first readily accessible" point inside the building?<br>
<br>
<br>
<br>
Best regards,<br>
<br>
<br>
<br>
Mark Dickson,<br>
<br>
NABCEP Certified Solar PV Installer T<br>
<br>
Oasis Montana Inc.<br>
<br>
<br><br></blockquote></div>