Kurt,<br><br>I worked on a elderly housing site in northern Ca in which we connected to the main service on each structure (total of 12) or building. These were about 2kw each and combined over three or four apartments and in some cases a full flat roof with a tilt up to 6kw. All of them were grid tied so a breaker in the panel was easy to put together the system. Labeling was accomplished by first the NEC and by PG&E requirements and disconnects were installed by the service. The nice thing about CA is they use only one meter which is a bi-directional digital system so the production meter was not needed.<br>
<br>Hope this helps a bit.<br><br>Jason<br><br><div class="gmail_quote">On Thu, Dec 25, 2008 at 9:52 AM, Kurt Albershardt <span dir="ltr"><<a href="mailto:info@es-ee.com">info@es-ee.com</a>></span> wrote:<br><blockquote class="gmail_quote" style="border-left: 1px solid rgb(204, 204, 204); margin: 0pt 0pt 0pt 0.8ex; padding-left: 1ex;">
We are looking at a project which has several small cottages on the property.  Each might have suitable roof area for ~1 kW or so of PV.  Each building has its own service, but we want to avoid installing multiple production meters, feeding the PV to a single aggregation & metering point on one of the structures.  Enphase inverters look like a good fit for this, but I am curious about disconnects & labeling.  Has anyone done a job like this?<br>

<br>
<br>
<br>
<br>
<br>
-- <br>
Kurt Albershardt<br>
Eastern Sierra Energy Engineering<br>
Reno, NV<br>
Silver City, NM<br>
<br>
_______________________________________________<br>
List sponsored by Home Power magazine<br>
<br>
List Address: <a href="mailto:RE-wrenches@lists.re-wrenches.org" target="_blank">RE-wrenches@lists.re-wrenches.org</a><br>
<br>
Options & settings:<br>
<a href="http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org" target="_blank">http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org</a><br>
<br>
List-Archive: <a href="http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org" target="_blank">http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org</a><br>
<br>
List rules & etiquette:<br>
<a href="http://www.re-wrenches.org/etiquette.htm" target="_blank">www.re-wrenches.org/etiquette.htm</a><br>
<br>
Check out participant bios:<br>
<a href="http://www.members.re-wrenches.org" target="_blank">www.members.re-wrenches.org</a><br>
<br>
</blockquote></div><br><br clear="all"><br>-- <br>Jason Lombard<br>Open Hand Solar LLC.<br>Certified Sustainable Building Adviser<br><a href="mailto:openhandsolar@gmail.com">openhandsolar@gmail.com</a><br>505 795 8646<br>
<br>"I'd put my money on solar energy… I hope we don't have to wait 'til oil and coal run out before we tackle that."<br><br>—Thomas Edison<br>