I used the term "critical loads subpanel" for many years until the NEC
specified that special meaning for medical equipment and such. I got caught
out by an AHJ official just as you did, Dan. I switched to "essential loads
subpanel" though "backed up loads subpanel" is probably more specific.
Dan Fink
Owner, Buckville Energy Consulting LLC
IREC Certified Instructor for PV and Small Wind Installation
NABCEP Certified PV System Inspector
NABCEP PV Associate
d <dan.fink at greendustrialtraining.com>anbob88 at gmail.com
970-672-4342
On Sat, Aug 9, 2025 at 11:46 AM William Miller via RE-wrenches <
re-wrenches at lists.re-wrenches.org> wrote:
> Ok: Priority loads.
> William Miller
> Miller Solar.com
> 805-438-5600
> www.millersolar.com
>
>
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20250809/ac681013/attachment.htm>
More information about the RE-wrenches
mailing list