[RE-wrenches] Zero sell permitting

Sam Haraldson sam at onsiteenergyinc.com
Tue Feb 11 15:06:32 PST 2025


>
> So to be clear. A zero sell is still required to get a net metered
> agreement?
>

Yes, for our particular utility a non-export (or as you're referring to it,
zero sell) system requires an approved interconnection agreement.  Once
installed the utility reserves the right to perform an in-person witness
test.