[RE-wrenches] Obscure PG&E NEM 3 question for CA Wrenchers

David Coale david at evcl.com
Tue Jan 14 22:10:48 PST 2025


This is an obscure PG&E NEM 3 related question for the California Wrenchers, since no one out side CA - PG&E land might be able to answer this.

I have a client with a 25 year old grid-tied system.  When PG&E went to smart meters they declined (worried about EMF) and have been able to hold on to their old mechanical meter and the old billing.

Now they want to upgrade to a new system as they are electrifying their home.  Does anyone know if they will still be able to hold on to their old meter and old billing?  I am guessing not and they just got lucky that PG&E has not forced them to get a new smart meter.  Seems like they found a loophole and did not really realize it.

Thanks,

David