[RE-wrenches] Direct Burial PV Wire?

Benn Kilburn benn at skyfireenergy.com
Tue Sep 27 14:11:14 PDT 2016


It is direct burial rated, as per the Canadian Electrical Code, Table 19.

*Benn Kilburn *
CSA Certified Solar Photovoltaic Systems Electrician, SkyFire Energy Inc
14515 – 121A Ave NW | Edmonton, AB | T5L 2T2
P: 780-474-8992 | F: 888-405-5843 | www.skyfireenergy.com
[image: email] <benn at skyfireenergy.com> [image: facebook]
<https://www.facebook.com/SkyFireEnergy> [image: twitter]
<https://twitter.com/SkyFireEnergy> [image: linkedin]
<https://www.linkedin.com/company/283735?trk=tyah&trkInfo=tarId%3A1408655033432%2Ctas%3Askyfire%2Cidx%3A2-2-5>


[image: SkyFire Energy Logo_horizontal]

*WE HAVE MOVED! Please note our new address above.*

On Tue, Sep 27, 2016 at 2:50 PM, Corey Shalanski <corey at joule-energy.com>
wrote:

> Umm, is PV Wire rated for direct burial? I have seen several manufacturer
> spec sheets that suggest this is the case, but I haven't heard of anyone
> ever actually doing this.
>
> Project Information:
> 1.6 MW single axis tracker
> (35) 40 kW string inverters
> Trenching from row ends to inverter wall, trench lengths will vary between
> 15-100 feet.
>
> --
> Corey Shalanski
> Joule Energy
> New Orleans, LA
>
> _______________________________________________
> List sponsored by Redwood Alliance
>
> List Address: RE-wrenches at lists.re-wrenches.org
>
> Change listserver email address & settings:
> http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
>
> List-Archive: http://www.mail-archive.com/re-wrenches@lists.re-wrenches.
> org/maillist.html
>
> List rules & etiquette:
> www.re-wrenches.org/etiquette.htm
>
> Check out or update participant bios:
> www.members.re-wrenches.org
>
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20160927/3f52f396/attachment-0002.html>


More information about the RE-wrenches mailing list