[RE-wrenches] Desired Posting
Drake
drake.chamberlin at redwoodalliance.org
Sat Feb 20 10:37:57 PST 2016
Hello Wrenches,
Are any upgrades needed on a distribution grid for interconnection,
other than bigger services for large arrays where existing equipment
is inadequate? Does the existing grid function fine as is, until a
saturation point is reached, which I have heard is around 25%?
After saturation is reached, what is needed to balance consumption
with generation? (How is this handled in Germany?) Is 25% an
accurate number for the saturation limit?
Thanks,
Drake
Drake Chamberlin
Athens Electric LLC
OH License 44810
CO License 3773
NABCEP Certified Solar PV
740-448-7328
<http://athens-electric.com/>http://athens-electric.com/
---
This email has been checked for viruses by Avast antivirus software.
https://www.avast.com/antivirus
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20160220/353ae43b/attachment-0002.html>
More information about the RE-wrenches
mailing list