[RE-wrenches] large array on 200 amp service

August Goers august at luminalt.com
Fri Sep 25 12:19:39 PDT 2015


Upgrading the main panel to 400 A but keeping the 200 A main breaker is
also an option. As always, there are many ways to achieve the code
compliant interconnection and typically one will stand out as being the
most cost effective while achieving the project goals.



Best,



August



*From:* RE-wrenches [mailto:re-wrenches-bounces at lists.re-wrenches.org] *On
Behalf Of *Jerry Shafer
*Sent:* Friday, September 25, 2015 11:50 AM
*To:* RE-wrenches
*Subject:* Re: [RE-wrenches] large array on 200 amp service



Line side tap with a fusable disconnect or a new service with dual main
load breakers. ( used in ag applications) There may be other requirements
also depending on AHJ
Jerry

On Sep 25, 2015 3:11 AM, "gary easton" <gary at arp-solar.com> wrote:

Hello Wrenches,

What are folks doing when installing 100A plus of solar into a 200A
service?



-- 

Gary Easton
Appalachian Renewable Power

Stewart, Ohio 45778
NABCEP Certified Solar PV

T: 740-277-8498

 www.arp-solar.com


“First they ignore you. Then they laugh at you. Then they fight you. Then
you win.”

~Ghandi




_______________________________________________
List sponsored by Redwood Alliance

List Address: RE-wrenches at lists.re-wrenches.org

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive:
http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
www.members.re-wrenches.org
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20150925/4daf76f5/attachment-0002.html>


More information about the RE-wrenches mailing list