[RE-wrenches] California wrenches PG&E

jay peltz jay at asis.com
Fri Jan 16 21:38:38 PST 2015


I am just asking about any advice for the paperwork process above 30kW with pg&e as I've never done one this large for a residence. 

Customer has a standard 400 amp 240v single phase connection. 

Thanks 

Jay

Peltz power 



> On Jan 16, 2015, at 5:25 PM, Jerry Shafer <jerrysgarage01 at gmail.com> wrote:
> 
> Well when you get that large the 3 phase makes a difference
> 
>> On Jan 16, 2015 5:23 PM, "William Miller" <william at millersolar.com> wrote:
>> Friends:
>> 
>>  
>> 
>> I would hesitate before offering three phase to a residential installation.  Well pumps, booster bumps and other appliance, if configured for 230 volts do not operate well with 208 volts.  They may work but you reduce your margin for voltage drop.
>> 
>>  
>> 
>> William
>> 
>>  
>> 
>>  
>> 
>> <image003.jpg>
>> Lic 773985
>> millersolar.com
>> 805-438-5600
>> 
>>  
>> 
>> 
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20150116/24c702c0/attachment-0002.html>


More information about the RE-wrenches mailing list