Kevin Pilcher kevin at renovusenergy.com
Thu Jul 24 12:39:02 PDT 2014


Wrenches,

We’d like to land a ground mounted PV system at a meter pedestal to avoid trenching back to the house. Establishing the PV system as a parallel service, we could drive a ground rod at the pedestal and land GEC at PV disconnect.

This brings up the auxiliary grounding issue discussed by Mike Holt in his 2014 code video.https://www.youtube.com/watch?v=YuDqXFvRv94.   

Is there any way to properly ground this system without trenching back to house?


Thank You,

Kevin Pilcher

Renovus Energy, Inc.
PV Systems Designer 
NABCEP Certified
607.277.1777 office
607.882.0539 cell
RENOVUSenergy.com