[RE-wrenches] Battery Back-up and Grid Tie
Bill Turberville
billturb at ece-llc.com
Fri Apr 26 10:01:49 PDT 2013
I live in a TVA area where there is a Feed In Tariff. Everything that is
generated by the PV array feeds into the grid through a Generation Meter
that ties-in ahead of the house meter. I have started getting calls from
customers who hate having a solar array that does not generate when the
grid is down but the sun is shining, but who also want to get the $.12
premium when the grid is connected. We have lots of systems with SMA
Sunnyboy inverters, but more with Enphase micro-inverters. Rather than
trying to reinvent the wheel, what you found to be the best solution for
this type of installation?
W.C. (Bill) Turberville P.E.
President
ECE Solar
Electrical Contracting Enterprises LLC
3080 Stage Post Road Suite 107
Bartlett, TN 38133
901-348-9230 ext 101 phone
901-348-2192 fax
901-289-6346 cell
billturb at ece-llc.com
NABCEP Certified PV Installation Professional 032611-320
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org/attachments/20130426/4002e8a8/attachment-0002.html>
More information about the RE-wrenches
mailing list