[RE-wrenches] rebar v/s fiber
Darryl Thayer
daryl_solar at yahoo.com
Fri Mar 12 09:56:48 PST 2010
I had a similar case the inspector would not allow without a rebar cage around the pole, and he wanted it on the plan, he accepted a dry stamp.
Darryl
--- On Fri, 3/12/10, bob <reellison at gmail.com> wrote:
> From: bob <reellison at gmail.com>
> Subject: [RE-wrenches] rebar v/s fiber
> To: "'RE-wrenches'" <re-wrenches at lists.re-wrenches.org>
> Date: Friday, March 12, 2010, 11:52 AM
>
>
>
>
>
>
>
>
>
>
>
>
>
>
>
> I
> have
> to put in a panel mount and am looking for advice as to
> whether concrete and
> rebar is the way to go or my concrete guy is recommending
> the fiber mixed into
> the concrete with no rebar.
>
>
>
>
> This
> will have to be a tall pole mount and I just wanted to pick
> the collective
> experience of the group.
>
>
>
>
> Any
> ideas as to how to go at this?
>
> Thanks,
>
>
> Bob
>
>
>
>
>
>
>
>
> -----Inline Attachment Follows-----
>
> _______________________________________________
> List sponsored by Home Power magazine
>
> List Address: RE-wrenches at lists.re-wrenches.org
>
> Options & settings:
> http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
>
> List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org
>
> List rules & etiquette:
> www.re-wrenches.org/etiquette.htm
>
> Check out participant bios:
> www.members.re-wrenches.org
>
>
More information about the RE-wrenches
mailing list