Interconnection info request [RE-wrenches]

Don Loweburg, Offline i2p at aol.com
Thu Mar 11 08:32:34 PST 2004


In a message dated 3/10/2004 3:24:31 PM Pacific Standard Time, 
allan at positiveenergysolar.com writes:
"the
qualifying facility to be designed by an engineer licensed in NM


Part of this problem is the language itself--"qualifying facility" usually 
describes a merchant plant or other wholesale generator-- not net metering--


Your net metering law - language must make a clear distinction between 
qualifying facilities and customer owned net metering installations. 

Best,Don

[Non-text portions of this message have been removed]

- - - -
To send a message: RE-wrenches at topica.com

Archive of previous messages: http://www.topica.com/lists/RE-wrenches/

List rules & etiquette: http://www.mrsharkey.com/wrenches/etiquete.htm

Check out participant bios: www.mrsharkey.com/wrenches/index.html

Hosted by Home Power magazine

Moderator: michael.welch at homepower.com
--^----------------------------------------------------------------
This email was sent to: michael.welch at homepower.com

EASY UNSUBSCRIBE click here: http://topica.com/u/?bz8Qcs.bz9JC9.bWljaGFl
Or send an email to: RE-wrenches-unsubscribe at topica.com

For Topica's complete suite of email marketing solutions visit:
http://www.topica.com/?p=TEXFOOTER
--^----------------------------------------------------------------






More information about the RE-wrenches mailing list