Interconnection info request [RE-wrenches]
Don Loweburg, Offline
i2p at aol.com
Thu Mar 11 08:32:34 PST 2004
In a message dated 3/10/2004 3:24:31 PM Pacific Standard Time,
allan at positiveenergysolar.com writes:
"the
qualifying facility to be designed by an engineer licensed in NM
Part of this problem is the language itself--"qualifying facility" usually
describes a merchant plant or other wholesale generator-- not net metering--
Your net metering law - language must make a clear distinction between
qualifying facilities and customer owned net metering installations.
Best,Don
[Non-text portions of this message have been removed]
- - - -
To send a message: RE-wrenches at topica.com
Archive of previous messages: http://www.topica.com/lists/RE-wrenches/
List rules & etiquette: http://www.mrsharkey.com/wrenches/etiquete.htm
Check out participant bios: www.mrsharkey.com/wrenches/index.html
Hosted by Home Power magazine
Moderator: michael.welch at homepower.com
--^----------------------------------------------------------------
This email was sent to: michael.welch at homepower.com
EASY UNSUBSCRIBE click here: http://topica.com/u/?bz8Qcs.bz9JC9.bWljaGFl
Or send an email to: RE-wrenches-unsubscribe at topica.com
For Topica's complete suite of email marketing solutions visit:
http://www.topica.com/?p=TEXFOOTER
--^----------------------------------------------------------------
More information about the RE-wrenches
mailing list